Employer: Liptovská vodárenská spoločnosť, a.s.
Contractor: ZIPP Bratislava, s.r.o. Mlynské Nivy 61/A, 820 15 Bratislava
Project Value: 19 489 956,8200 EUR € excl. VAT
Commencement Date: 1st. October 2010
Completion Date: 31st. December 2012, one year test operation, construction is in operation from 1/2014
Project Description
Intensification of WWTP Liptovský Mikuláš was focused on completing and modernizing the WWTP. It included the demolition of old buildings, construction of new facilities, renovation of existing facilities, replacement and installation of technological equipment and other equipment in the context of the intensification of the wastewater treatment plant (hereinafter "WWTP") Liptovský Mikuláš to 126,400 PE.
Main contractor: Dopravoprojekt, Inc.
Restado Ltd. carried out activities "Construction Supervision Expert No.1" eg Construction Supervision Engineer for Waste Water Ttreatment